on if the hard parts are good just have a local shop re-tube it and be done with it .
agreed that cut/strech job is funky and the welds even more so .
and looking further the front slip yoke is 90* off from the correct clocking position .
Just did my front shaft and it for sure wasn't key'd.
And now after hearing this I know it's also out of phase lol. When I took it out they were 45* to each other... So I put it back that way.
That is a spare, at best.
Mine was definitely keyed. It had one spline that was wider than the rest so it could only line up one way and slip on.

Maybe newer, or after market..?
Neither one of my front shafts are.
One is stock 81 1-ton, other is ???
then they welded the slip and yoke section on 90* off from the correct position .The slip yoke splines are keyed so it can go on only one way...at least that the way my front driveshaft on my Dana-60 is.