I admit to caulking down intakes once or twice. Never tried a head gasket though.


The only gaskets I have ever bought is tranny gaskets not including the pan, head gaskets and occasionally intake gaskets for engines that mean something.
 
Crazy is checking 1 main bearing and 2 rod bearings for clearances, saying "good nuff" then promptly running it out of oil at a mudfest it went to the day it got running.

Its the 454 in my suburban. And it doesn't burn nor drop a bit of oil. Luck is a fickle beast.
 
I don't understand how it's possible to "run out of things to do" prior to Blazer Bash.....I thrashed till 3 am and left at 5am several years and still felt like there was more to do...Everything tight? Everything tied down? All the tools packed? Everything greased? Extra fluids? Etc. etc. etc. ad nauseam....
 
I don't understand how it's possible to "run out of things to do" prior to Blazer Bash.....I thrashed till 3 am and left at 5am several years and still felt like there was more to do...Everything tight? Everything tied down? All the tools packed? Everything greased? Extra fluids? Etc. etc. etc. ad nauseam....
First time out to Moab I was welding up roll cage at 1 am the day we were leaving. Moab thrash is a thing

If he ran out of stuff to do, it's because he sucks at ordering parts
 
This list has probably shrunk a little

Here is my 2017 Blazer Bash prep list, it isn't in any particular order.
  1. Learn to weld
  2. build front receiver/ tow point cross member
  3. Install Air bumps
  4. Install limit straps
  5. Trim Fenders
  6. Install new water pump
  7. install new oil pan
  8. install charcoal canister
  9. clean up under hood wiring
  10. install cb radio
  11. install cb antenna
  12. install radio
  13. install speakers
  14. install fuse block
  15. mount ecm
  16. mount engine fuse block
  17. mount obd2 port
  18. install seat cover
  19. install transfer case shifter
  20. install trans and transfer case breather
  21. install power windows
  22. install door panels
  23. install parking brake
  24. install new o ring on fuel sending unit
  25. vent gas tank to charcoal canister
  26. extract broken bolt in diff cover
  27. install gov lock
  28. install receiver hitch
  29. Install rock lights
  30. install and build brackets for the 6 inch light bars in the turn signal front bumper.
  31. reseal transfercase
  32. A surprise if I can get it done before MOAB
Also trying to leave about 3 weeks before the bash to do a shake down trail run. This thing was essentially tossed together for BB15 and I have been trying to keep it running sense, the engine and 5 transmissions set me back a lot and haven't been able to work on this list like I had hoped to.
 
18 days until the bash. :eek: I'm so far behind it isn't funny. Today the rear diff will go back together, take it for a test drive to make sure it works then I'll pull the tcase for reseal.

Going to make orders to ord, and chassis unlimited today.
 