Digging into electrical hookup for the shed. The pump house has power already, so the plan is to connect there and trench over to the shed.

My main house panel has 200A service with a 125A circuit feeding my shop, long overdue for an update, but not failing yet.
20260619_193052.jpg20260619_193059.jpg

In the shop, 125A main with 30A feeding pump house.
20260619_193213.jpg20260619_193216.jpg20260619_193226.jpg

In the pump house, 100A main feed with 10 ga and many empty slots. the 100A would likely never do anything, but the 30A feeding it should be good given the wire size. the 20A circuit in the pump house is the submerged well pump, the 15A is two lights in the shed with LED bulbs. A 3/4 horse submerged well pump should draw 6-8 amps when in use.
20260619_193354.jpg

My plan is 10 ga feeding the sub panel in the shed on a 30A 220VAC breaker for now, but long term I may want to pull bigger wires for more power to the pump house (currently buried in larger than needed conduit) in order to get 50-60A service in the shed.

I have installed 3x 20A 120VAC circuits with 12ga wiring for outlets and lighting. All lighting will be LED.
20260619_193326.jpg

My current thinking is this should not cause any problems. But I'm leaving the ability to pull larger feed wires and upsize the breakers if needed later, likely when I upgrade my house panel and run a dedicated 200A service into the shop.
 