Eric and I will be working on it from Wed to Mon.
The plan is to build up the cage, rock sliders, boatside, engine compartment cage, shock hoops, bumpstops and mounting, and whatever else come along to complete those items. Also high priority is figuring both axle pinion angles so I can complete the welding on the rear and make any necessary adjustments to the front.
Also get the rear Gauntlet bumper mounted!!!!!!!!
Wrenching items will be whatever is on my build list to complete, from where I'm at on the list at the time. So whatever someone feels comfortable working on, but basically I'm here right now:
Weld on mounts for Spring limiting blocks (for trailering to limit suspension travel)
Figure oil coolers mounting
Fabricate oil cooler lines
REMOVE DRIVETRAIN/STRIP FRAME
Clearance around pass side header
blast and zinc coat inside of frame rails
Weld up frame boxing kit
Sandblast exterior frame
Clean and seam seal any double layered plates
Paint frame
Body back on frame
Check floor mods for raised fuel tank
Clean underbody and paint
Rock sliders
Mini Boat side
Cage installation
Shifter mounting
Seating
Seat belts
Cup holders
Driver reachable storage
Grab handles
Major component completion
............Rear 14BFF axle:
Final weld rear shock mounting
Final weld rear spring perches
Paint rear axle/springs/all brackets/shackles etc
Install truss/Antiwrap mounting plates
Install pinion guard
Finish weld Antiwrap bars, and add gusset
....................Front Dana 60 axle:
check wheel studs for proper fit
check all lugnuts for proper application
figure shock mounting
..................Engine:
Align crankshaft pulley
Install temp sender
Install oil cooler adapter
Install oil pressure sender
Valve cover venting
Vacuum advance source
make vac.mech advance adjustments
.....................Transmission:
TH400, install trans temp sender unit and other mods needed
Torque convertor cover mounting holes
Shifter cable hookup
Check pan seal
Install dipstick tube
......................203/205 Doubler:
Dis-assemble the 205 for replacement of the front output, add a spacer, replace the shifter rails w/ ORD rails for triple stick, drill and tap for a sightglass oil level tube.
Drill and tap for 203 sightglass oil level tube
Fab and install transfer case venting system
Locktite everything doubler related.
Misc. items
Route Hydroboost lines
Figure trans temp guage placement and needs
Fab and install axle t/c venting system
Fabricate battery mount
Install battery master shutoff
Install remote starter solenoid
Run Battery cables
Mount front winch bumper
Install and wire Windstar fans